Akron Cleveland Road & Barlow Road Traffic Signal - Status update

Print

 

Current plans are for SCE forces to install the traffic signal this year. Our office has completed the initial survey of the intersection and provided mapping to TMS of Stow to prepare the detailed traffic signal drawings.  As soon as we have the information to order the traffic signal poles, an order will be placed for the 4 strain poles.  Normal delivery time for poles is 14 to 16 weeks.  During the time the poles are being fabricated, we anticipate installing the foundations and some of the underground conduits.  Once we receive the final plans we will order the rest of the signal parts and as soon as we take delivery of the various items, final construction will begin.  This office anticipates a traffic signal at the location in late fall of 2010.