Construction : Canton Road Resurfacing - 2023 Project

LAST UPDATED:

Oct 22, 2024

Project Details

Project ID:

115358

Communities:

Springfield Township

Project Contacts:

Brian Olson

Project Schedule

Plan Year:

04-01-2023 - 11-30-2023

Construction Starts:

Jul 15, 2024

This project provides for the resurfacing of Canton Road from Pontius Road to Tisen Road. A special round of AMATS funding applications was conducted in June 2021 and SCE was awarded $528,000. This was additional STBG monies from AMATS, with an 80/20 match ratio. The money came from the Coronavirus Response and Relief Supplemental Appropriations Act.

Status:

Design is substantially complete.
Northstar has been awarded this contract.

  • 05/21/2024: Working on getting preconstruction meeting set up with contractor.
  • 06/14/2024: Preconstruction meeting was held
  • 07/02/2024: Contractor will be starting work on July 15th weather permitting. 
  • 0/7/09/2024: Contractor has stated that they will start work on catch basins on Thursday 7/11/2024
  • 07/15/2024: Work on this project was began. Northstar has started pavement milling
  • 07/23/2024: Contractor has began paving (leveling course)
  • 07/30/2024: Paving is complete
  • 08/06/2024: Burming is being completed this week along with manhole covers. 
  • 08/13/2024: Work is being done on guardrail along with loop detectors. 
  • 08/20/2024: Work was being completed on manhole covers
  • 08/27/2024: Working on pouring concrete patches this week
  • 09/03/2024: Contractor has formed areas for concreter repair
  • 09/24/2024: Contractor should be finishing up concrete repairs this week or early next
  • 10/01/2024: Work should be completed by Friday
  • 10/15/2024: Project is substantially completed.
  • 10/22/2024: No changes. SCE looking at completing final walkthrough with contractor. 
Graphical map of project site

Maintenance of Traffic:

Traffic will be maintained throughout the project. 

Image of Canton Road Resurfacing Project Image 2023

Costs

Project Development Cost:

$100,000.00

Construction Cost:

$700,000.00

Total:

$800,000.00

Funding Sources:

Federal Funds: $572,000

Motor Vehicle and Gas Tax Funds: $272,000.00