Completed : NOW OPEN! - N. Revere Road Bridge over Revere Run Replacement
LAST UPDATED:
Nov 12, 2024
Project Details
Communities:
Bath Township
Project Contacts:
Neal Miesle, PE
Project Schedule
Plan Year:
08-01-2022 - 10-05-2024
Construction Starts:
Aug 5, 2024
The project will replace the current corrugated metal pipe bridge (BAT-114-0320) built in 1965 with a precast concrete box culvert. This will be a design/build project.
Status:
Kenmore Construction has the contract for this design/build project. Design is complete.
- 11/16/2023: Dominion gas company have moved one of their lines.
- 03/21/2024: Work was delayed due to EPA restiriction. Construction to follow once restrictions are lifted.
- 06/13/2024: Kenmore has set new start date for July 15th, weather permitting,
- 07/23/2024:Contractor has informed SCE that project start date has been moved to August 5,2024
- 07/30/2024: Work is set to begin on August 5,2024.
- 08/06/2024: Bridge is closed and exsisting structure will begin to be removed this week.
- 08/13/2024: Contractor is still removing the exhisting structure
- 08/27/2024: Dated structure has been completely removed. Contractor plans to set box this Thursday, weather permitting
- 09/03/2024: Boxes have been set and installing waterpeoofing membrane.
- 09/17/2024: Contractor is pouring headwalls and will start back filling.
- 09/24/2024: Completed backfill and starting to install rock channel protection.
- 10/01/2024: Guardrail is to be installed tomorrow 10/02.
- 10/15/2024: Project is substantally completed and open at this time.
- 11/12/2024: Contractor is addressing erosion on site
Maintenance of Traffic:
The road will be closed and traffic detoured during construction of the new bridge. Signs will be posted.