Completed : SWMD - Wye Road Drainage Improvements Phase 1

LAST UPDATED:

May 1, 2024

Project Details

Communities:

Bath Township

Project Contacts:

Dave Koontz, PE

Design Consultant:

ms consultants, inc

Project Schedule

Plan Year:

11-01-2023 - 12-31-2024

This project will be done in two phases. Phase 1 will install improved storm sewers and swales at two locations in the Sanctuary of Bath Estates. 

Status:

Cook Paving was awarded this contract.

  • 02/20/2024: Contractor started pavement repairs
  • 02/27/2024: Contractor continues to work on pavement repairs along with storm sewer.
  • 03/19/2024: Contractor has contacted gas company to have gas line lowered.
  • 03/26/2024: Utility company will be out this week to lower gasline.
  • 04/02/2024: Contractor will be out mid April to finish topsoil and seeding, weather permitting. 
  • 04/29/2024: Contractor has completed seeding.

At this time the project is completed.

Location:

In Bath Township benefitting the Yellow Creek Watershed. 

Image of Wye Road Map

Costs

Construction Cost:

Phase 1 - $205,118.00

Funding Sources:

Phase 1 design is funded by Bath Surface Water Management District. 

Phase 1 construction is funded by the Bath Surface Water Management District (10%) and the Ohio Emergency Management Agency (90%.)