Design : SWMD - Wye Road Drainage Improvements Phase 2

LAST UPDATED:

Jul 24, 2024

Project Details

Communities:

Bath Township

Project Contacts:

Dave Koontz, PE

Design Consultant:

ms consultants, inc

Project Schedule

Plan Year:

06-01-2023 - 06-01-2025

This project will be done in two phases. Phase 2 will modify existing stormwater management basins and add best management practices such as step-pools, cascades, and riffles at four locations along the stream in the ravine at the northern edge of the Sanctuary of Bath Estates It will also include cleaning out an existing storm sewer along Wye Road and perform minor clean up and erosion repairs along the stream. 

Status:

Design for Phase 2 is about 95% complete with construction scheduled for Fall of 2024 through Spring of 2025.

Location:

In Bath Township benefitting the Yellow Creek Watershed. 

Image of Wye Road Map

Costs

Construction Cost:

Phase 2 - $1,000,000.00

Funding Sources:

Phase 2 design is funded by Bath Surface Water Management District.

Phase 2 construction will be funded by American Rescue Plan Act dollars and the Ohio Emergency Management Agency.